Resource Leveling Options – Leveling Sensitivity

By default, Microsoft Project notifies of overallocation on a day-by-day basis. Although that may be sufficient for some projects, other levels of sensitivity may be more appropriate such as week-by-week, or month-by-month.

 

In the following illustration, Bradley Beck and Wendy Wheeler are overallocated as defined by the default leveling sensitivity setting of Day by Day:

Resource Overallocation Leveling Options Leveling Sensitivity Pic1

To change leveling sensitivity to week-by-week, from the Resource tab, Level group, click Leveling Options as shown in the following illustration:

Resource Overallocation Leveling Options Leveling Sensitivity Pic2

From the Resource Leveling dialog box, change leveling sensitivity to Week by Week as shown in the following illustration:

Resource Overallocation Leveling Options Leveling Sensitivity Pic3

Once OK is selected, Bradley Beck and Wendy Wheeler are no longer denoted as overallocated as shown in the following illustration:

Resource Overallocation Leveling Options Leveling Sensitivity Pic4

Applies To: All Current Versions of Microsoft Project.