Updating task status updates resource status

UpdateTaskStatusPic1

By default, the option Updating task status updates resource status is selected in Microsoft Project. For example, when a % Complete value is entered, Microsoft Project will automatically enter a % Work Complete value when work is scheduled during the % Complete period as shown in the following illustration:

UpdateTaskStatusPic2

If, in this example, a  % Work Complete value had been entered, Microsoft Project would have automatically entered a % Complete value.

UpdateTaskStatusPic3

When the option Updating task status updates resource status is not selected, the percent complete fields may be updated independently of one another. For example, when you enter a % Complete value, Microsoft Project will not enter a % Work Complete value when work is scheduled during the % Complete period as shown in the following illustration:

UpdateTaskStatusPic4

Please note; however, that regardless of the option setting, when 0% or 100% is entered in either percent complete field, Microsoft Project will change the other percent complete field to match!

Option Location: Schedule page of the Project Options dialog box

Applies to: Microsoft Project, all versions

 